OGR-28 status update

Filed under: project status @ 02:21 +00:00

Dear friends,

I wrote back in February that we estimated the first two subspaces of OGR-28 would take us about 90 days to complete. I must apologise; it has taken us 3 times as long.

As we reached the end of these two spaces, we had a day where we completed over 1 million stubs. Of course, most of them were very small indeed. There will be more days like this to come.

We can consider the project as a range of “hills” and “valleys”. At the beginning of the climb, the steps are slow and difficult. Having passed the peak, we can take steps downhill quickly with little effort. We started the project with 32 hills to climb. We have completed the first one. Good news! The other 31 aren’t so tall!

There are just over 9,000 of us working together on this research. We are grateful for all of your contributions. Tell a friend; let us see if we can get to 10,000 before Thanksgiving. :)

Moo!